Free business guide
Building permissions for apartments and commercial buildings in India: a beginner’s guide
The approval journey for a new building, explained for beginners.
At a glance
| Item | What it means | Who decides |
|---|---|---|
| Land-use / zoning check | Is the plot zoned for residential, commercial, etc. under the Master Plan? | Town-planning / development authority |
| Building plan sanction | Permission for your drawings (height, floors, setbacks, parking) | Municipal corporation / municipality / development authority |
| NOCs | Fire, airport height, environment, water/sewer, power, water bodies, trees etc. | Each department; many states route them through one portal |
| Commencement permission | Permission to actually start construction | Local authority |
| RERA registration | Needed before you advertise or sell if the project crosses the threshold | State RERA authority |
| Construction-stage controls | Inspections, plan compliance, structural and fire safety | Local authority, your professionals |
| Completion / occupancy certificate | Proof the building was built as sanctioned and is safe to occupy | Local authority |
| After completion | Property tax assessment, electricity, water and sewer connections | Municipality, power distribution company, water board |
| RERA threshold (Central Act, section 3) | Land over 500 sq m or more than 8 apartments (all phases counted) | State RERA authority |
Steps (in order)
Step 1: Check the land and its permitted use
Before drawing anything, confirm that the plot can legally carry your type of building.
– Ask the town-planning section of the local authority for the Master Plan / zoning of the plot: residential, commercial, mixed use, industrial, water body, green belt, etc. A building that does not match the zone cannot be sanctioned.
– Where the land is agricultural or in another zone, a land-use change / conversion is needed first. Several states handle this on the same online portal as building permission.
– Have your title checked by a property lawyer (title chain, encumbrance certificate, approved layout, road access). This guide does not cover title.
– Documents usually needed: title documents, encumbrance certificate, survey/land sketch, owner’s ID, and any layout approval.
Step 2: Hire the professional team
You cannot file most applications alone. Authorities work through registered professionals, and many publish lists of registered architects, engineers, structural engineers and supervisors.
| Role | What they do |
|---|---|
| Architect | Designs the building, prepares drawings that follow zoning, FSI, setback and parking rules, files the application and usually coordinates NOCs. |
| Structural engineer | Designs foundation, columns, beams and slabs for the soil and loads; signs the structural drawings. |
| Licensed surveyor | Measures the plot, prepares the boundary and site plan, and (for airport height clearance) provides surveyed coordinates and site elevation, which AAI requires from a qualified or government-authorised professional or agency. |
| Site supervisor / engineer | Where the authority registers supervisors, oversees day-to-day construction against the sanctioned plan. |
| Lawyer | Title, development agreement, sale agreement. Not the same as the architect. |
Check that each professional is registered with the local authority for your city.
If you live abroad (NRIs): you can run the project remotely, but you need people on the ground.
– Appoint a local architect and structural engineer registered with the authority of the city where the plot is, and a local property lawyer.
– Give written authority through a properly executed power of attorney drafted by your lawyer, and confirm what the authority and the bank accept. Do not hand over blank signed papers.
– Ask for copies of everything filed: application, drawings, fee receipts, sanction, NOCs, commencement permission and the occupancy certificate.
– Arrange a trusted person or site engineer for stage-wise photos and inspection reports, and check the sanctioned plan yourself against what is being built.
– Confirm separately, with a chartered accountant or bank, the rules on remitting money and on taxes for NRIs.
Step 3: Understand FSI/FAR, setbacks and parking
These three controls decide how much you can build. Each city sets its own numbers in its zoning or development regulations, so use your local rules.
– FSI / FAR (floor space index / floor area ratio): total permitted floor area divided by plot area. The MoHUA Model Building Bye-laws use “FAR” and express table values as multiples, so 180 means 1.8 times the plot area. Illustration (not a rule for any city): on a 1,000 sq m plot at FAR 1.8 the total floor area allowed is 1,800 sq m. Mezzanine floors count toward FAR; some basements used only for parking or services may be excluded.
– Ground coverage: the share of the plot the building footprint may cover. The Model Bye-laws also expect part of the open area to be landscaped.
– Setbacks (open spaces): the minimum gap between the building and the front, rear and side boundaries. They vary with plot size and building height and are set by the Master Plan or development plan.
– Parking: counted in “equivalent car spaces” (ECS) per 100 sq m of floor area. The Model Bye-laws give 18 sq m per ECS for open parking, 23 sq m for covered ground-floor parking and 28 sq m for basement parking; the ECS requirement itself comes from the local development plan.
– How the numbers are decided in practice: usually by plot size, width of the abutting road, building use (residential or commercial) and height. Tamil Nadu, for example, sets minimum plot size, road width, FSI, coverage and maximum height for each category of multi-storeyed building.
Step 4: Apply for building plan / planning permission
- Who approves: the municipal corporation, municipality or development authority for the area.
- How: most states now use an online system (see the state examples). The typical flow: register as the applicant or professional, upload documents and drawings, pay the initial processing fee, wait for scrutiny and site inspection, pay the remaining fees on demand, and download the sanction and approved drawings.
- Documents usually needed: ownership documents, plot survey and site plan, architectural and structural drawings in the format the portal asks for, professional registration details, NOCs where applicable, and fee receipts. The exact checklist is on each authority’s portal; confirm with the authority.
- Bengaluru’s online system, as published by BBMP, shows a typical chain: online form, fee, document verification and automated drawing scrutiny, site inspection, recommendation by town-planning officers, then final approval and issue of the building licence and demand note.
- Read the conditions of any sanction. Permissions obtained by false declaration can be cancelled.
Step 5: Technical clearances and NOCs
Which NOCs you need depends on size, height, use and location. Many states bundle them in one portal.
| NOC / clearance | When it applies | Who gives it |
|---|---|---|
| Fire | Taller buildings and public-use buildings (offices, malls, schools, halls). Height and area thresholds are set state by state. | State Fire Services department |
| Airport height clearance | Structures near airports where height may affect flight paths. AAI’s online NOCAS system is used; AAI’s guidelines say a building NOC is valid for 5 years, with limited revalidation. Confirm current rules. | Airports Authority of India |
| Environmental clearance | Large building and township projects above a built-up-area threshold need environmental clearance. Confirm the current threshold and the authority with your State Environment Impact Assessment Authority. | State / Central environment authority |
| Water bodies / irrigation | Plots near lakes, rivers, ponds and drains often need irrigation and revenue NOCs. | Irrigation, Revenue |
| Water and sewer | Large developments need water supply and drainage arrangements approved. | Water board / municipality |
| Electricity | Load sanction and new connection, applied for with the power distribution company. | Power distribution company |
| Trees and other | Tree felling or transplantation permissions and other local NOCs may apply. | Forest / horticulture / municipality |
Step 6: Commencement permission
After sanction, most authorities expect a commencement certificate or equivalent before you lay the foundation. In some cities it is a separate document (Bengaluru’s town-planning pages list “Commencement Certificate” as a separate service); in others it may be part of the sanction proceedings. Confirm with your authority and do not start work before it.
Step 7: RERA registration
- Rule (Central RERA Act, section 3): a promoter must register the project with the State RERA before advertising, marketing, booking or selling. The MoHUA FAQ (July 2025) says projects are exempt if the land is 500 sq m or less, or if they have eight or fewer apartments, including all phases. So land above 500 sq m or more than eight apartments triggers registration. Telangana’s RERA FAQ spells out both cases.
- Prior approvals: Telangana RERA’s FAQ says to obtain building or layout permissions from the competent local authority before applying for registration.
- Other points from the MoHUA FAQ: the authority must decide within 30 days or the project is deemed registered; the advance or booking amount is capped at 10% before an agreement for sale is signed; 70% of buyers’ money is to be kept in a separate project bank account for construction and land cost; major changes to sanctioned plans need allottees’ consent as set out in section 14.
- Penalty: Telangana’s FAQ cites a penalty of up to 10% of the project’s estimated cost for non-registration, with possible imprisonment for continued violation. Other states set penalties under their own rules; confirm with your State RERA.
- Quote the RERA registration number in advertisements.
Step 8: Construction-stage controls
- Build exactly as sanctioned: same floors, height, footprint, setbacks and parking.
- Expect site inspections at stages in several states; keep the approved plan, structural drawings and test records at site.
- Any change (extra floor, changed layout) needs a revised sanction.
- Keep to the fire safety, lift, rainwater and other conditions of sanction; they are checked at completion.
Step 9: Completion / occupancy certificate
- The completion/occupancy certificate (OC) confirms the building was completed as per the sanctioned plan and conditions and is fit for occupation. You apply to the same authority, usually on the same portal; the authority inspects and issues it if the building matches the approved plan.
- Small individual houses are exempt in some states (Telangana exempts individual residential buildings on plots up to 200 sq m and 7 m height built with valid permission). Apartments and commercial buildings need an OC.
- Under RERA, sale deeds are tied to the OC: Telangana RERA’s FAQ says the promoter must execute the conveyance deed within three months of the OC or when 51% of buyers have paid in full, whichever is earlier.
- Do not occupy, hand over flats or take possession payments before the OC is in hand.
Step 10: After completion: property tax and utilities
- Property tax: the building must be entered in the municipality’s assessment records. Apply to the municipal corporation or municipality with the sanction and OC; procedures vary by city.
- Electricity, water and sewer: permanent connections are normally issued after the OC. Apply through the power distribution company and the water board.
- Fire safety certificates may need periodic renewal; confirm with the state Fire Services.
- For apartments, form the owners’ association and hand over common areas as the law and your lawyer advise.
State notes
Examples from four states
Use these to see how the same steps look in practice. They are examples, not a substitute for checking your own city.
Telangana
– TG-bPASS (tgbpass.telangana.gov.in) is the state’s single online platform under the Telangana Municipalities Act, 2019. It offers building permission, occupancy certificates, tentative layout approval, land use and conversion certificates and post-verification.
– Categories: up to 75 sq yards, ground or G+1 residential: no permission or OC needed, only online registration with a Rs 1 token. Up to 500 sq m and 10 m height residential: instant permission through self-certification. Above 500 sq m or 10 m, plus commercial, high-rise, group housing and apartments: single-window NOCs through a Common Application Form.
– The TG-bPASS FAQ lists a 21-day processing period with deemed permission after 21 days, shortfalls communicated within 10 days, and compliance within 15 days or automatic rejection. Self-certification makes the applicant personally liable for false declarations, and violations may lead to demolition without notice.
– Plots within the bed of notified water bodies cannot be approved; plots abutting water bodies need Irrigation and Revenue NOCs.
– GHMC’s online process: application, site inspection by an Assistant City Planner, review up the chain, Building Committee decision, fee calculation, payment and proceedings.
– RERA: Telangana RERA (rera.telangana.gov.in).
Andhra Pradesh
– Building permission is processed through the state’s online building-permission portal (confirm the current name on the municipal or town-planning website), by the municipal body, development authority or Directorate of Town and Country Planning depending on where the site is. Confirm which authority covers your site.
– Confirm FSI, setback, parking, NOC and OC rules with that authority, and registration steps with AP RERA.
Tamil Nadu
– The Tamil Nadu Single Window Portal for Planning Permission (onlineppa.tn.gov.in), run by the Housing and Urban Development Department, processes planning permission, building permission, completion certificate, reclassification and layout applications for DTCP, CMDA and other planning bodies. CMDA says no manual submission of drawings is accepted and only online payment is honoured, and that NOC integration is live for 10 departments.
– Planning permission and building permission are separate; both are needed. The TN FAQ says planning permission may be issued within a maximum of 45 days if documents follow the checklist and plans meet norms, and is valid for 3 years, renewable once for 3 years (apply a month before expiry).
– A multi-storeyed building is one with more than 4 floors and a height of 15 m or more; the FAQ lists maximum FSI values from 1.5 to 2.50 depending on category.
– On the portal you either request an NOC or upload one already approved, and respond online to any particulars letter.
– RERA: TNRERA (rera.tn.gov.in).
Karnataka
– In Bengaluru, BBMP’s online system covers building plan sanction, commencement certificate and occupancy certificate. Under the Greater Bengaluru Governance Act, 2024, a Greater Bengaluru Authority is the planning authority and up to seven city corporations are provided for; BBMP ceases to exist once the final notification is issued. Confirm which body currently sanctions plans for your site.
– Outside Bengaluru, building sanction is with the city or town municipal body; confirm the portal and process with it.
– RERA: K-RERA (rera.karnataka.gov.in); confirm registration steps there.
Other states
- Building permission: search for “[your city name] building permission online” on the municipal corporation, municipality or development authority website, or check the state urban development / town and country planning department site. Confirm you have the right body for your plot (city limits, development authority area, or panchayat).
- RERA: every state and union territory has its own RERA authority and website under the Central Act, with its own forms and fees. Search for “[state] RERA” and make sure the site is a government (.gov.in) address. The MoHUA FAQ is a good plain-language start.
- Ask the local architect which portal they file on and ask to see the checklist before you commit.
Common mistakes and red flags
- Building more than the sanctioned plan (extra floor, bigger footprint, setback encroachment). Deviations can lead to penalties or demolition and block the OC.
- Unauthorised floors and penthouses sold off-plan. Check the sanctioned plan and the OC before buying.
- Starting work on a self-certified or deemed approval without reading its conditions.
- No OC. Without it, utility connections, bank loans and resale become hard.
- Selling before RERA registration where the project crosses the 500 sq m / 8 apartment threshold.
- Skipping the fire or airport NOC because the building seems small. Thresholds depend on height, use and location.
- Plots on or near water bodies, or in the wrong zone.
- Splitting a project into phases to stay under the RERA limit. RERA counts all phases together.
- Using unregistered architects, engineers or surveyors.
- Expired sanction or NOC. Planning permissions and NOCs have validity periods; track them.
- Relying on a broker’s word. Ask for the sanction proceedings, commencement certificate, RERA number and OC.
- Taking advances beyond the RERA cap or not using the separate project bank account.
This is general information, not legal advice. Use a property lawyer for title and agreements, and a registered architect and structural engineer for design.
Official websites
- tgbpass.telangana.gov.in
- tgbpass.telangana.gov.in/others/faq
- ghmc.gov.in/Building.aspx
- rera.telangana.gov.in/Uploads/BU_150923163734953.pdf
- mohua.gov.in/static/uploads/2025/12/542144159b61c980253a694f478d3a5d.pdf
- mohua.gov.in/static/uploads/2025/12/c97038f7a5e435c64a01a91ea649c1ba.pdf
- crmapp.mcgm.gov.in/irj/go/km/docs/documents/EODB/BuildingCircular/AAI/NOCASGuidelines1stOct2014.pdf
- onlineppa.tn.gov.in/faq
- onlineppa.tn.gov.in/sites/default/files/2023-06/TNSWPP_NOC_Applicant_User_Manual_Updated.pdf
- onlineppa.tn.gov.in/sites/default/files/2024-02/Building_plan_After_Dtcp_Approval.pdf
- cmdachennai.gov.in/onlineppa.html
- rera.tn.gov.in
- site.bbmp.gov.in/buildingplan.html
- site.bbmp.gov.in/townplanning.html
- site.bbmp.gov.in/PDF/buildingplanapproval/SimplifiedOnlineApplicationSubmissionProcedure.pdf
- indiacode.nic.in/bitstream/123456789/21664/1/36_of_2025_(e
This guide is general information to help you get started. It is not legal, tax or professional advice, and rules, fees and dates change. Confirm each step on the official website and with a qualified professional, such as a chartered accountant or company secretary, before you act.